Processing
- Month/Quarter/Year Processing
- M - Month
- Q - Quarter
- Y - Year
Specify whether to generate the TCS certificate monthly, quarterly, or yearly. Values are:
M: Month
Q: Quarter
Y: Year
- Enter Month (If monthly processing)
- Range 1 - 12
Specify the numeric value for the month for which you want to run the report. For example, enter 1 for January.
- Enter Quarter (Only for Quarterly processing)
- Range 1 - 12
Specify the roman value for the quarter for which you want to run the report.
- Assessment Year
- Enter the year for which the ube should run.
- Eg. If Year entered is 2009, Month entered is 1 then data of January 2010 will be processed.
Specify the year for which you want to run the report. This is the assessment year.
For example, if you specify M as the type of processing, the month as 1, and the year as 2011, the report prints details for January 2011. If you enter the month as 5 in the above example, the report prints details for May 2010. However, if you specify Y as the type of processing and specify the year as 2011, then the system runs the report for the period from April 2010 through March 2011.
In all these cases, the system displays the assessment year on the report as 2011-2012.