Processing

1. Enter the tolerance amount.

Specify the tolerance amount.

The system calculates the bid contract price variance between the JD Edwards EnterpriseOne Procurement and JD Edwards EnterpriseOne Homebuilder Management systems. The system compares this variance to the tolerance amount that you enter in this processing option. If the variance is greater than or equal to the tolerance amount, the report includes the bid contract price.

2. Enter the tolerance percentage.

Specify the tolerance percentage. For example, enter 0.15 for 15 percent.

3. Enter a '1' to select only positive variances, a '2' for only negative variances or leave blank for both.

Specify whether to select positive or negative variances or both. Values are:

Blank: Positive and negative variances.

1: Positive variances only.

2: Negative variances only.

4. Enter the bid document type to be used.

Enter a code from UDC 00/DT that specifies the bid document type. Leave this processing option blank to select all document types.

5. Specify the report code (1 through 4) to be used as the variance reason code.

Specify the UDC table to use for the variance reason code. Values are:

1: UDC 41/P1

2: UDC 41/P2

3: UDC 41/P3

4: UDC 41/P4