Queries for the Lot Start Coordinator Persona

The queries for the lot start coordinator persona are associated with the Lot Master (P44H201), Sales Workbench (P44H500), Homebuilder Purchase Order (P44H703), and Lot Start Workfile Maintenance (P44H711) programs.

The following table lists and describes the queries available for the lot start coordinator:

Query Name

Program

Criteria

Projected Starts

Lot Master (P44H201)

  • Construction Completion Date is between 01/01/2003 and today's date

You must modify the date range for the Construction Completion Date in the query based on your requirements.

Under Construction

Sales Workbench (P44H500)

  • Close Date is < 01/01/1950

  • Construction Start Date is < Today

You must modify the date range for the Close Date in the query based on your requirements.

Projected Closings

Sales Workbench (P44H500)

  • Close Date is < 01/01/1950

  • Projected Close Date is >= Today

You must redefine the Projected Close Date as today's date plus the number of days in the future that you would like to see.

Unapproved EPOs

Homebuilder Purchase Order (P44H703)

  • Default data selection

Estimated Quantities

Lot Start Workfile Maintenance (P44H711)

  • Commitment Posting Status = E

Unassigned TBD

Lot Start Workfile Maintenance (P44H711)

  • Commitment Posting Status = T

  • TBD record is not assigned to a supplier

Wokfile On Hold

Lot Start Workfile Maintenance (P44H711)

  • Commitment Posting Status = H

Workfile Unposted

Lot Start Workfile Maintenance (P44H711)

  • Commitment Posting Status = Blank