Method C (Percent Complete from Cost Code Header)

You assign method C when you want to use the percent complete from the header account to calculate the final projected values for the detail accounts. You must use method C in conjunction with either method P or method Q, or the system uses actual values (AA and AU) as projected final values (HA and HU) for the detail accounts.

  • Assign to detail accounts.

  • If you assign method P to the header account, the system uses the value of PC (F%) for the detail account that is assigned method C.

  • If you assign method Q to the header account, the system calculates PC for the detail account that is assigned method C using the formula AU / HU * 100.