Prerequisites
Before working with forecasts, you must complete the following steps:
Verify that the accounts included in the forecast have a start and an end date in the Cost Code Schedule table (F51901).
Note: If an account does not have a planned start date or actual start date, the system uses the build date from the Forecast Header table (F5101) as the forecast start date.Verify that the accounts included in the forecast have budget amounts.
Set up revenue and cost automatic accounting instructions (AAIs) for base company and job company. Revenue accounts include the account range of JCCA01 – JCCA02. Cost accounts include the account range of JCST01 – JCST02.
For a summary forecast, set the processing options in the Create Summary Forecast program (R5112).
For a detail forecast, set the processing options the Create Detail Forecast program (R5111).