Versions
Use these processing options to select the application versions to execute. If you leave any of these processing options blank, the system uses version ZJDE0001.
- 1. Original Budget Version (P510121)
Specify the version of the Original Budget program (P510121) to use when the program is accessed from the Row menu.
- 2. Job Status Inquiry Version (P512000)
Specify the version of the Job Status Inquiry program (P512000) to use when the program is accessed from the Row menu.
- 3. Budget Revision Version (P510171)
Specify the version of the Budget Revision (P510171) to use when the program is accessed from the Row menu.
- 4. Job Supplemental Data Version (P00092)
Specify the version of the Supplemental Data program (P00092) to use when the program is accessed from the Row menu.
- 5. Copy Job to Job Version (P51091)
Specify the version of the Copy Job to Job (P51091) program to use when the program is accessed from the Row menu.
- 6. Cost Code Schedule Version (P51901)
Specify the version of the Cost Code Schedule (P51901) program to use when the program is accessed from the Row menu.
- 7. Purchase Orders Version (P4310)
Specify the version of the Purchase Orders program (P4310) to use when the program is accessed from the Row menu.
- 8. Select button exits
Specify which application to run when you select a record from the Work with Job Master form. Values are:
Blank or 1: Job Master Revisions
2: Job Revisions by Company
3: Original Budget
4: Budget Revisions
5: Copy Similar Jobs
6: Cost Code Schedule
7: Update Percent Complete
8: Extended Job Master