Retainage Calculations
This equation shows how the system calculated the percent complete:
(Net Amount) ÷ (Schedule of Values) = Percent Complete |
---|
7,200.00 ÷ 12,000.00 = 0.60 |
These equations illustrate how the system calculated the total retainage:
Percent Complete |
(Schedule of Values) × (Retainage Completion) × (Retainage Percentage) = (Retainage Amount) |
---|---|
20 percent |
12,000.00 × 0.20 × 0.10 = 240.00 |
38 percent - 20 percent = 18 percent remaining to be calculated |
12,000.00 × 0.18 × 0.15 = 324.00 |
Total |
240.00 + 324.00 = 564.00 |
This table shows how the system calculated the retainage for each billing line:
Billing Line |
(Net Amount) ÷ (Total Net Amount) × (Retainage Amount) = (Billing Line Retainage Amount) |
---|---|
001 |
1,200.00 ÷ 7,200.00 ×564.00 = 94.00 |
002 |
6,000.00 ÷ 7,200.00 × 564.00 = 470.00 |