Retainage Calculations
This table shows how the system calculated the percent complete for each billing line:
Billing Line |
(Net Current Amount) ÷ (Schedule of Values) = Percent Complete |
---|---|
001 |
1,200.00 ÷ 5,000.00 = 0.24 |
002 |
6,000.00 ÷ 12,000.00 = 0.50 |
This table shows how the system calculated the retainage for billing line 001:
Billing Line |
(Schedule of Values) × (Percent Complete) × (Retainage Percentage) = Billing Line Retainage Amount |
---|---|
001 |
5,000.00 × 0.20 ×.10 = 100.00 |
001 |
5,000.00 × 0.04 ×.15 = 30.00 |
Total |
100.00 + 30.00 = 130.00 |
This table shows how the system calculated the retainage for billing line 002:
Percent Complete |
(Schedule of Values) × (Percent Complete) × (Retainage Percentage) = Billing Line Retainage Amount |
---|---|
20 percent |
12,000.00 ×.20 × 0.10 = 240.00 |
38 percent – 20 percent = 18 percent remaining to be calculated |
12,000.00 ×.18 × 0.15 = 324.00 |
50 - 0.38 (retainage completion already calculated) = 12 percent complete on billing line |
12,000.00 ×.12 × 0.25 = 360.00 |
Total |
240.00 + 324.00 + 360.00 = 924.00 |