Retainage Calculations

This table shows how the system calculated the percent complete for each billing line:

Billing Line

(Net Current Amount) ÷ (Schedule of Values) = Percent Complete

001

1,200.00 ÷ 5,000.00 = 0.24

002

6,000.00 ÷ 12,000.00 = 0.50

This table shows how the system calculated the retainage for billing line 001:

Billing Line

(Schedule of Values) × (Percent Complete) × (Retainage Percentage) = Billing Line Retainage Amount

001

5,000.00 × 0.20 ×.10 = 100.00

001

5,000.00 × 0.04 ×.15 = 30.00

Total

100.00 + 30.00 = 130.00

This table shows how the system calculated the retainage for billing line 002:

Percent Complete

(Schedule of Values) × (Percent Complete) × (Retainage Percentage) = Billing Line Retainage Amount

20 percent

12,000.00 ×.20 × 0.10 = 240.00

38 percent – 20 percent = 18 percent remaining to be calculated

12,000.00 ×.18 × 0.15 = 324.00

50 - 0.38 (retainage completion already calculated) = 12 percent complete on billing line

12,000.00 ×.12 × 0.25 = 360.00

Total

240.00 + 324.00 + 360.00 = 924.00