Earned Value Calculations
The following table describes the earned value calculations:
Column Name |
Calculation |
|---|---|
Earned Value |
Budget At Completion * Percent Complete |
Cost Variance |
Earned Value - AA Job to Date |
Cost Performance Index |
Earned Value / AA Job to Date |
Schedule Variance |
Earned Value - JA Job to Date |
Schedule Performance Index |
Earned Value / JA Job to Date |
Estimate At Completion |
Budget At Completion / Cost Performance Index |
Estimate To Completion |
Estimate At Completion - AA Job to Date |
Variance At Completion |
Budget At Completion - Estimate At Completion |
Status |
(Cost Performance Index + Schedule Performance Index) / 2 |
Unit Cost |
AA Job to Date / AU Job to Date |
Budget At Completion |
Total Planned Units Job To Date * Unit Cost |