Costing Modified Work Orders for Configured Items in ETO

Once the configuration for a root configured item has been defined in the Configured Item Revisions program and all child configured work orders have been created, the estimated costs should be updated in the Project Workbench program (P31P001) for all root and child configured work orders. This update is applicable during the generation of child configured work orders via definition of the configuration and during the changing of an existing configuration.

Important: When a new root configured work order is added to the Workbench structure, Estimated Costs should not be updated.