Adding Products to a Process Map

Access the Manage Process Maps form.

Assign Products

Click to access the Work With Selected Items form, where you can select the products that you want to include in the process map. This form also displays the product synchronization that you have defined for the product.

Remove Products

Click to remove products from a process map and exclude them from the selected volume design.

SSOE (standard sequence of events)

Enter the name of the standard sequence of events that you want to use as source for labor and machine resource times. When you enter a standard sequence of events in this field, the system retrieves the cumulative resource times for the process and displays them in the SSOE Machine (sequence of events machine) and SSOE Labor (sequence of events labor) fields.

SOE Machine (sequence of events machine) and SOE Labor (sequence of events labor)

Display the total machine and labor times for the process if you have defined a sequence of events for the process. The process map retrieves these values from the FF30L117 table.

Note: If these values do not match the labor and resource totals in the FF30L110 and FF30L115 tables, run the Event Summary Update program (RF30L117).
Actual Machine and Actual Labor

Enter resource time estimates for the process manually.

Design Selection

Select a value from the Demand Sequence UDC table (F30L/DS) to indicate which work content value the system uses in line design to calculate actual time weighted (ATW) for labor and machine operations by process. Values are:

ACT: Actual times.

SOE: Sequence of events.

STD: Standard sequence of events.

Define Cells by Machine and Define Cells by Labor

Click to access the Define Cells Using Work Content form, where you can split the process into cells.

Define Machine Resources and Define Labor Resources

Click to access the Actual Work - Edit Work Content form, which enables you to enter multiple resources and resource times for the process. The process map displays the total resource time by resource type.

Save Changes

Click to save changes to the process map. If you have changed and recalculated the product synchronization, you must click this button to save these changes to the database, even though the changes are already visible in the grid.

View Time Map and View Commonality Map

Click to access the View Time Map and the View Commonality Map form. To view the most up-to-date information, you must have saved the changes to the process map before you access these forms