Defining Kanban Pull Chains
Access the Add Pull Chain form.
- Consumption Location
Enter the location where components or raw materials will be consumed in a kanban pull chain.
- Consumption Branch Plant
Enter the branch/plant of the consuming location.
- Supply Location
Enter the location from which components or raw materials have been transferred to a consuming location in a kanban pull chain.
- Supply Branch Plant
Enter the branch/plant of the supplying location.
- Package UOM (package unit of measure)
Enter a code from user-defined code 00/UM that indicates how items are transported between locations.
- Insert Sequence Above
Click to add a row to the pull chain. The first consumption location is on the line from supply. In the next sequence, the supply location from the previous sequence becomes the consumption location.
- Delete Sequence
Click to delete the selected sequence.