Planning Parameters

Select the Planning Parameters tab.

DFM Shipment Preparation Time

Enter a value that you use to calculate the recommended completion date in the Daily Planning and Sequencing program. You subtract the number of days that you enter here from the promised ship date of the sales order to arrive at a completion date.

Select Branch Calendar

Click to display the Search for Work Day Calendar form. Select a branch-specific calendar for association with the scenario that you are setting up. The planning system uses this calendar for back scheduling.