R40R030: Shipment Analysis
The Shipment Analysis report (R40R030) enables you to compare the required shipping date with the actual shipping date. You can configure the output of the report with these types of information:
The percentage of items that were shipped early.
The percentage of items that were shipped on time.
The percentage of items that were shipped late.
All records.
You can specify tolerance levels for time and quantity in the Shipment Analysis processing options on the Display tab, which enables you to establish the timeliness of shipments. For example, suppose you specify that thirty minutes is the tolerance for the Early Shipment Tolerance Level (Time) processing option. If the actual shipping date and time of an order is thirty minutes or less before the requested shipment date and time, the system considers the order to be on time.
The system uses the F40R41 table to process information for the Shipment Analysis report.