Scheduling the Project

Access the Edit And Lock All Tasks form.

Note: Scheduling from the Edit And Lock All Tasks form is only at the project level.

Schedule the tasks that you entered in the WBS using the Forward Schedule and Backward Schedule buttons on the form.

To schedule tasks:

  1. On Edit And Lock All Tasks, select Forward Schedule or Backward Schedule and click the Schedule button.

  2. In the detail area, review the adjusted planned start and planned end dates.

    The date adjustment depends on the task dependencies that you defined, as well as the duration of each task.