Mfg Mode

1. Process Planning

Specify whether the system performs planning for process manufacturing. If you use process manufacturing, enter 1 to generate the plan based on the forecasts of the co/byproducts for the process. The program then creates messages for the process. Values are:

Blank: Discrete

1: Process

2. Project Planning

Specify whether the system includes supply and demand from items that are associated with Engineer to Order (ETO) projects or Project Manufacturing production numbers.

ETO project-specific items have a Special Handling Code of type P. Values are:

Blank: Do not include items associated with ETO projects or Project Manufacturing production numbers.

1: Include items associated with ETO projects.

2: Include items associated with Project Manufacturing production numbers.

3. Configurator Components Table

Specify whether the system processes configurator components from the Configurator Component table (F3215) and adds them to the Sales Order Detail File table (F4211) and the Work Order Parts List table (F3111). If you enter a 1 in this processing option, the system processes the items on the Configurator Component table as demand items.

Blank: Do not process items from the Configurator Component table.

1: Process items from the Configurator Component table.