General

These processing options control whether the actual dates are displayed and whether the Work Order Status batch process is run automatically. These processing options are specific to weigh tag operations.

1. Enter Actuals

Specify whether the system enables you to enter actual dates. Values are:

Blank: Do not allow users to enter actual dates.

1: Allow users to enter actual dates.

For future use.

2. Run Calculate Work Order Status (R31B19)

Specify whether the Work Order Status batch process is run immediately following the addition of a work order. The Work Order Status batch process uses the operation statuses to determine the work order status. Values are:

Blank: Do not automatically run the Work Order Status batch process.

1: Run the Work Order Status batch process automatically.

3. Re-Schedule Operations Flag

Specify whether you want to reschedule the operations flag. Values are:

Blank: Do not reschedule operations.

1: Reschedule operations.

4. Default Operation Status (Release 9.2 Update)

Use this processing option to specify the status that the system should assign to the newly created operations. You can assign the status as Draft, Active, or Actual. If you leave this blank, the system assigns the status as Draft.