This diagram shows the information that you can update using the Speed Update program (P31B96)

Speed Operation Update.

You use the Speed Operation Update program (P31B96) to change the operation status to active, actual, or closed. You can also assign a job number to the operation.

The system recalculates the elapsed time when you change either the instructed start time or the instructed end time. However, if you change the elapsed time, the system does not recalculate the instructed end date.

You can edit equipment and resources also. You cannot edit spray and farm information using this program.