Prerequisite Setup

The demand profile for the item is:

Date

Source

Quantity

October 6

FC

100

October 8

FWO

300

October 15

SO

200

October 17

SO

350

November 6

FC

150

The MPS Regeneration program (R3482) ran for five days, four weeks, and three months. The resulting time series is:

Date

Demand Type

Demand As Of Date

Comment

October 6

FC

100

October 7

October 8

FWO

300

October 9

October 10

October 17

SO

550

October 24

October 31

8 periods in MRP Window

November 7

FC

150

November 28

December 31

January 30

The calculation method has been set up using the Kanban Size Calculation Definition program (P3017). The calculation method has calculation-specific parameter values, as defined in the Kanban Size Calculation Parameter Definition program (P3018).

Parameter

Parameter Value

Periods in MRP Window

8

Days built per week

5

Days built per month

20

Scan delta days

1

lead time delivery (days)

2

Vendor split percent

100

Safety stock

50

Demand split percent

100

Container size

25