Prerequisite Setup
The demand profile for the item is:
Date |
Source |
Quantity |
---|---|---|
October 6 |
FC |
100 |
October 8 |
FWO |
300 |
October 15 |
SO |
200 |
October 17 |
SO |
350 |
November 6 |
FC |
150 |
The MPS Regeneration program (R3482) ran for five days, four weeks, and three months. The resulting time series is:
Date |
Demand Type |
Demand As Of Date |
Comment |
---|---|---|---|
October 6 |
FC |
100 |
|
October 7 |
|||
October 8 |
FWO |
300 |
|
October 9 |
|||
October 10 |
|||
October 17 |
SO |
550 |
|
October 24 |
|||
October 31 |
8 periods in MRP Window |
||
November 7 |
FC |
150 |
|
November 28 |
|||
December 31 |
|||
January 30 |
The calculation method has been set up using the Kanban Size Calculation Definition program (P3017). The calculation method has calculation-specific parameter values, as defined in the Kanban Size Calculation Parameter Definition program (P3018).
Parameter |
Parameter Value |
---|---|
Periods in MRP Window |
8 |
Days built per week |
5 |
Days built per month |
20 |
Scan delta days |
1 |
lead time delivery (days) |
2 |
Vendor split percent |
100 |
Safety stock |
50 |
Demand split percent |
100 |
Container size |
25 |