Time Series for Production Controlled Items

Use the appropriate version of the MPS Time Series program (P3413) to review the item series for the material requirements plan.

See “Analyzing Planning Output" in the JD Edwards EnterpriseOne Applications Requirements Planning Implementation Guide.

The MPS Time Series program does not contain any specific functionality for production controlled items. The time series displays only quantities that are not associated with production numbers. Thus, any work orders, purchase orders, or sales orders tagged to a production number do not affect the time series. You can review production number information in the Production Number Workbench program (P34403).

If the Suppress Time Series processing option on the Performance tab of the MRP/MPS Requirements Planning (R3482) and Master Planning Schedule - Multiple Plant (R3483) programs is set to blank to generate the time series, then the time series may contain invalid data.