Entering Costing and Accounting Information for Work Centers

Access the Work Center Rate Revisions form.

(Release 9.2 Update) You can also access the Work Center Rates – Mass Update form to add or update more than one work center's rates at a time. You can manually add or update the records, or you can import the records from a csv file or clipboard to perform a mass update.

Cost Method

Enter a UDC (40/CM) that specifies the basis for calculating item costs. Cost methods 01 through 19 are reserved for use by the JD Edwards EnterpriseOne system.

Direct Labor

Enter a rate, in cost per person per hour, that the system uses with the run labor hours of the associated routing to calculate the standard run labor cost.

Setup Labor

Enter a rate that the system uses with the setup labor hours of the associated routing to calculate the standard setup labor cost.

Labor Variable O/H (labor variable overhead)

Enter a rate or percent, as determined on Manufacturing Constants, used to calculate the standard variable labor overhead cost. If this field is a rate, it is the cost per hour. If this field is a percent, it is the percent of direct labor.

Enter percents as whole numbers. For example, enter five percent as 5.00.

Labor Fixed O/H (labor fixed overhead)

Enter a rate or percent, as determined on Manufacturing Constants, used to calculate the standard fixed labor overhead cost. If this field is a rate, it is the cost per hour. If this field is a percent, it is the percent of direct labor.

Enter percents as whole numbers. For example, enter five percent as 5.00.

Machine Run

Enter a rate that the system uses with the Run Machine hours of the associated routing to calculate the standard machine labor cost.

Machine Variable O/H (machine variable overhead)

Enter a rate or percent, as determined on Manufacturing Constants, used to calculate the future standard machine overhead cost. If this field is a rate, it is the cost per hour. If this field is a percent, it is the percent of machine run.

Enter percents as whole numbers. For example, enter five percent as 5.00.

Machine Fixed O/H (machine fixed overhead)

Enter a rate or percent, as determined on Manufacturing Constants, used to calculate the standard fixed machine overhead cost. If this field is a rate, it is the cost per hour. If this field is a percent, it is the percent of machine run.

Enter percents as whole numbers. For example, enter five percent as 5.00.