Project

1. Consider Items Involved in Project

Specify whether to consider items involved in a project.

Blank: Do not consider items involved in project.

1: Consider items involved in project.

2: Check whether items involved in project need to be considered.

2. Closed Work Order Status

Enter a user-defined code (00/SS) that describes the status of a work order, rate schedule, or engineering change order. Any status change from 90 through 99 triggers the system to automatically update the completion date.