Reviewing the Feature Cost Percentage for Kit Items

Access the Enter Bill of Material Information form.

Feat Plan % (feature planned percent)

Enter the percentage of demand for a specified feature based on projected production. For example, a company might produce 65 percent of their lubricant with high viscosity, and 35 percent with low viscosity, based on customer demand. The JD Edwards EnterpriseOne Requirements Planning system uses this percentage to accurately plan for the co-products and by-products of a process. Enter percentages as whole numbers, for example, enter 5 percent as 5.0. The default value is 0.

Feat Cost % (feature cost percent)

Enter the percentage that the Cost Simulation program uses to calculate the cost of a feature or option item as a percentage of the total cost of the parent. Enter percentages as a whole numbers, for example, enter 5 percent as 5.0.

R (required)

Enter a code that specifies whether a component is required. Values are:

Y: The component is required.

N: The component is not a required selection during order processing. The default value is N.

DC (default component)

Specify an item as a default component. Use this field if you are creating sales orders using the Recurring Orders Edited Creation program (P40211Z). To do so, enter Y in this field. When you specify a kit master item, the Recurring Orders Edited Creation program automatically selects all related standard and default components.

Opt (S/O/F) (optional item (standard/optional/feature))

Enter a code that indicates whether a component is standard or optional within a bill of material or for kit processing. Values are:

S: Standard.

The item is always included in any transaction involving the bill of material.

O: Optional.

In order entry, you can specify whether the item will be included in a particular sale.

F: Feature.

The item has features that you must specify at order entry.

The default value is S.