This table lists related tasks:

Task

Description

Evaluating tests during Bulk Load Confirm

The test type that you specify in the Test Revisions program (P3701) determines whether you enter test results during the Bulk Load Confirm process. If a test is required, the Bulk Load Confirm process stops until you enter passing test results. If a test is optional, a warning message appears, but you can complete the Bulk Load Confirm process. If a test is guaranteed, you can complete the Bulk Load Confirm process, and no warning message appears.

Creating nonconforming records

When you enter test results, you can also write failed tests to the F3703 table. Set the Record Nonconforming Product processing option on the Test Results tab for P3711. Use the Nonconforming Product program (P3703) to view these records.