Bill of Material

MRP uses the bill of material to explode demand to all component items. If a parts list does not exist for a work order, MRP generation uses the standard bill of material to explode demand.

You should define a bill of material type M (standard manufacturing bill) for work order headers without a parts list and for parent planned orders. The MRP generation uses bill type M to schedule items according to how the product is built.