Defaults

These processing options specify the defaults used for processing.

1. Enter the Capacity Mode

Specify a code indicating which level of planning is being used. Values are:

1: Resource Requirements

2: Rough Cut Capacity

3: Capacity Requirements

2. Enter the default Unit of Measure

Specify a UDC (00/UM) that identifies the unit of measurement for an amount or quantity. For example, it can represent a barrel, box, cubic meter, liter, hour, and so on.

3. Enter the version of the Dispatch List to call

Specify a user-defined set of specifications that control how applications and reports run. You use versions to group and save a set of user-defined processing option values and data selection and sequencing options. The default version is ZJDE0001.