Defining Resource Profiles Manually

Access the Resource Profile Revisions form.

Unit Type

Enter a code that indicates the type of resource unit that is associated with this work center.

Possible types are:

1: Run Labor Hours

2: Setup Labor Hours

3: Machine Hours

9: Miscellaneous (storage space and so on)

Effective From

Enter a date that indicates:

  • When a component part goes into effect on a bill of material.

  • When a routing step goes into effect as a sequence on the routing for an item.

  • That when a rate schedule is in effect, the default is the current system date.

    You can enter future effective dates so that the system plans for upcoming changes. You can continue to record and recognize items that are no longer effective in the future in JD Edwards EnterpriseOne Product Costing, JD Edwards EnterpriseOne Shop Floor Management, and Capacity Requirements Planning. Material Requirements Planning determines valid components by effectivity dates, not by the bill of material revision level. Some forms display data based on the effectivity dates you enter.

Effective Thru (effective through)

Enter a date that indicates:

  • When a component part is no longer in effect on a bill of material.

  • When a routing step is no longer in effect as a sequence on the routing for an item.

  • When a rate schedule is no longer active.

    The default is December 31 of the default year that is defined in the Data Dictionary for Century Change Year. You can enter future effective dates so that the system plans for upcoming changes. You can continue to record and recognize items that are no longer effective in the future in JD Edwards EnterpriseOne Product Costing, JD Edwards EnterpriseOne Shop Floor Management, and Capacity Requirements Planning. Material Requirements Planning determines valid components by effectivity dates, not by the bill of material revision level. Some forms display data based on the effectivity dates that you enter.

Time Basis

Enter a UDC (30/TB) that indicates how machine or labor hours are expressed for a product. Time basis codes identify the time basis or rate to use for machine or labor hours that are entered for every routing step (for example, 25 hours per 1,000 pieces or 15 hours per 10,000 pieces). You can maintain the time basis codes in the Time Basis Codes UDC (30/TB).

The system uses the values in the Description-2 field on the User-Defined Code form for costing and scheduling calculations. The description is what the code represents, but it is not used in calculations.