Parallel

These processing options specify the number of processors that the system uses during parallel processing. These options also specify whether the system runs preprocessing during parallel processing.

1. Number of Subsystem Jobs

Specify the number of subsystems in a server.

The default is 0 (zero).

2. Pre Processing

Specify whether the system runs preprocessing during parallel processing. During preprocessing, the system checks supply and demand and plans only the items within supply and demand. Preprocessing improves performance when you run MRP and is valid only when the number of items actually planned is less than the total number of items in the data selection. Values are:

Blank: Do not run preprocessing.

1: Run preprocessing.