Planning Family Messages
You can manually review and process messages using the MRP/MPS Detail Message Revisions program or automatically process the messages using the MRP/MPS Detail Message Processing program (R3411).
The action messages for DRP, MPS, and MRP are defined in UDC table 34/MT. The character codes are hard-coded. Do not change the character codes in this list.
Each time that you generate a material requirements plan, the system generates action messages to identify situations in which demand requires:
Changing the existing supply orders.
Placing new orders.
Use the Message Detail - MRP version of the MRP/MPS Detail Message Revisions program to review exception messages from the latest planning generation. These messages might help you evaluate planned and existing orders. You can review the most critical messages first and review other messages in the order that you process them.