Process

These processing options enable you to specify the branch that a system uses for the CRP/RCCP Regeneration program (R3382) and the percentages for underrated and overrated capacity. Additionally, you determine whether you want work centers to be rolled up by dispatch group in the planning.

1. Branch

Specify the branch that the system uses for the CRP/RCCP Planning Regeneration program.

2. Under Rated Capacity Percent

Specify the tolerance percent under the rated capacity that the system uses to determine whether a work center is underloaded. The system displays messages with a status of U (under) for capacity loads that are less than the identified percentage under the rated value.

For example, if the rated capacity is 100 units and the underrated capacity is set to 5 percent, then the system still considers a capacity load of 95 units as a valid load at a work center. Similarly, the system would consider a capacity load of 94 units as an underload.

3. Over Rated Capacity Percent

Specify the tolerance percent over the rated capacity that the system uses to determine whether a work center is overloaded. The system displays messages with a status of O (over) for the capacity load that is greater than the identified percentage over the rated value.

For example, if the rated capacity is 100 units and the overrated capacity is set to 5 percent, then the system still considers a capacity load of 105 as a valid load at a work center. Similarly, the system would consider a capacity load of 106 units as an overload.

4. Roll Up To Dispatch Group

Specify whether multiple work centers within a dispatch group roll up to that dispatch group for review. Values are:

Blank: Do not roll up work centers to a dispatch group.

1: Roll up work centers to a dispatch group.