Reviewing Critical Component Alerts

To review critical component alerts:

  1. Access the Planning Console form.

    Form Name

    Form ID

    Navigation

    Planning Console

    W34X200A

    • Click the Item No. link in the Item Number field of the Item Summary grid in the Planning Summary program (P34X100).

    • DRP Daily Operations (G3411) or MRP Daily Operations (G3413).

      Select Planning Console (P34X200).

  2. On the Planning Console form, review the following alerts in the Critical Component Alerts group in the Planning Selection group, as applicable:

    DOS (days of supply alert count)

    Displays a value that represents the number of critical components that have critical days of supply issues in a certain period of time for a specific parent item or sub assembly.

    EA (ending available alert count)

    Displays a value that represents the number of BOM or parts list components that have a negative ending available balance in a certain period of time for a specific parent item or sub assembly.

  3. Click the DOS or EA link, as applicable to access the Critical Component Summary form.

  4. Review critical components.

    See Managing Critical Components.