Understanding Multifacility Plan Generation

After you have set up the supply and demand relationships among the branch/plants, you can use the Distribution Requirements Planning (DRP), Master Production Scheduling (MPS), and MRP gross regeneration versions of Master Planning Schedule - Multiple Plant to generate a multifacility plan. Alternatively, you can use the DRP, MPS, and MRP net change versions of Master Planning Schedule - Multiple Plant to generate a multifacility plan.

When you generate a multifacility plan, the system evaluates selected information, performs calculations, and recommends a time-phased plan for all selected items.