Completing Work Orders Against Demand Flow Daily Plans

Access the Search for Demand Flow Plan form.

To complete work orders against Demand Flow Daily Plans:

  1. Select the daily plan against which you want to complete work orders on the Demand Flow Plan form.

  2. Click the Complete Item button.

  3. Enter completion and scrap quantities as needed on the Work Order Completion Detail form.

    Note: If you are reversing a completion, enter negative quantities.
  4. Click OK.