Dates and Quantities

Select the Dates and Qtys tab to complete these fields:

Requested

Enter the date that an item is scheduled to arrive or that an action is scheduled for completion.

For the JD Edwards EnterpriseOne Shop Floor Management system, when you change the requested date these processes occur:

  • The system calculates a new start date based on the new requested date if you delete the date in the Start Date field before you enter the new requested date.

    If you do not delete the start date, the system does not recalculate or change it.

  • The system recalculates the operation start and complete dates according to the scheduling rules defined.

Order/UOM (order/unit of measure)

Enter the quantity of units affected by this transaction.

For JD Edwards EnterpriseOne Shop Floor Control Discrete Manufacturing, when you change the order quantity, the system recalculates:

  • The component-required quantities and commitments.

  • The operation start and complete dates, if the lead times are variable.

  • In the process industry: the quantity of co-products and by-products produced by the process.

Planned Effective

Enter the date that the work order or engineering change order is planned to be completed.

Start

Enter the start date of the work order.