Edits

These processing options specify whether the system automatically updates the parts list and routing when rate quantities and dates change, and validates existing item branch records when you add rate schedules.

1. Update Parts List and Routing

Specify whether the system automatically recalculates parts list quantities, routing quantities, and dates when you change rate schedule quantities or rate schedule dates from the Enter/Change Rate Schedule program (P3109). Values are:

Blank: Do not recalculate parts list quantities, routing quantities, or dates.

1: Update parts list, routing quantities, and dates.

2. Validate Existing Branch/Item Records

Specify whether the system validates an existing item/branch record when you add or update a rate schedule. Values are:

Blank: Do not validate.

1: Validate.