Prerequisites

Before you complete the tasks in this section:

  • Before completing process work orders:

  • Set the appropriate processing options to access the Inventory Issues program (P4112) and to identify the version of the program to use.

  • Set the appropriate processing options to issue ingredients for each co-product and by-product separately, and to enable completion of unplanned co-products and by-products.

  • Before releasing sales backorders during completions, set processing options to call the Backorder Release program (P42117) and identify the version to use.