Variable Lead Time

If an item on the work order has a variable lead time, the system determines the start date by using the lead time per unit to backschedule. The system uses this calculation:

[((Leadtime per unit × order quantity) / Time basis code unit value) + Setup + Total queue] / Work hours per day

For example, assume:

  • Work order due date = October 15.

  • Lead time per unit = 32 hours.

  • Work order quantity = 1000.

  • Setup = 1 hour.

  • Queue (including move time) = 9 hours.

  • Time basis code = 10,000 (code 4, which indicates 10,000 units).

    This information is from the Item Branch File table (F4102).

  • Work hours per day = 8.

[((32 hours × 1000) / 10000) +1 hour + 9 hours] / 8 hours = 1.65 days

The system calculates the start date by counting back two working days on the shop floor calendar from the due date. The work order start date is October 13.

Note: (Release 9.2 Update) Based on the setting in the Work Order Start Date Update processing option of the Work Order Routing program (P3112), the system updates the work order start date to match the routing start date for the first operation for an item with a variable lead time.