Setting Up Advanced Preferences for GOP Sourcing
Set up Advance Preferences only if you want to source the Branch/Plant from GOP.
To configure advanced preferences:
Run the Preference Values Definition (F40711) Update report (R40711S) to insert the preference details into the Preference Values Definition table (F40711).
This is a one-time setup before configuring the advance preferences.
Set up a new preference for GOP in the Preference Definition Revisions form.
See also: Setting Up Preference Definitions.Set up preference details for the GOP preference that you created, using the Preference Detail Revisions form.
See also: Setting Up Preference Details.Advanced Preference Type - Verify that the value 47 - GOP Preference exists in UDC 40/AP. This value specifies how the system processes an advanced preference adjustment.
Set up preference detail values using the Preference Values Revisions form.
See also: Setting Up Preference Detail Values.Define a schedule for the advance preference using the Preference Schedule Revisions form.
See also: Setting Up Preference Schedules.Attach the GOP schedule that you created to the processing option of the sales order version (P4210).
Enter P4210 in the Interactive Versions field and click Find.
Select the program version (GOP version), and then select Processing Options from the Row menu.
Select 5 - Commitment from the drop-down menu and set 1. Activate Availability Checking as Blank or 2 so that the system does not back order the Order line.
Select 10-Preference from the drop-down menu.
Set the Preference Profile Processing to 1 and enter the schedule that you defined for GOP sourcing in the Override Schedule for Advanced Preferences field and then click OK.