Use this AAI to determine the allowable cost types (objects) for the contracts.

You must follow these guidelines when you set up CT AAIs:

  • The first two characters must be CT.

  • The second two characters indicate the contract type, such as OS and OP.

    You must create a separate CT AAI for each contract type. You must also define the contract types in the UDC table for document types (00/DT).

  • The last two characters must be a numeric value from 01 to 99.

    This value uniquely identifies each valid cost type within the contract type.

  • Do not assign company, business unit, or subsidiary to the CT AAIs.