PeopleSoft Grants and PeopleSoft Project Costing-Related Invoice Correction Example
The following example demonstrates the PeopleSoft Grants and PeopleSoft Project Costing-Related Invoice Correction functionality.
An invoice that contains charge errors is created. To correct the erroneous invoice, a credit and rebill is completed. Invoice A in the example reflects the charges on the original invoice. Invoice B represents the credit invoice. Invoice C reflects the charges on the rebill.
| Billing Activity | Invoice A | Invoice B | Invoice C |
|---|---|---|---|
|
Supplies |
800.00 |
(800.00) |
800.00 |
|
Equipment |
400.00 |
(400.00) |
400.00 |
|
Total |
1,200.00 |
(1,200.00) |
1,200.00 |
A journal entry adjustment is completed and sent to PeopleSoft Billing. Invoice C now contains the following additional bill activity:
| Invoice C Billing Activity | Invoice C Amount |
|---|---|
|
Supplies |
800.00 |
|
Equipment |
400.00 |
|
Equipment (from journal entry) |
(400.00) |
|
Total |
800.00 |