Progress Payment Business Process Flow
The following list identifies the steps for setting up and processing a progress payment:
-
Create a contract with a contract classification of Government.
-
Add amount-based contract lines to the contract associated with progress payment amounts.
Note:
Government contracts can include amount-based or rate-based (Time and Material or fee associated) contract lines on the same contract. However, progress payments can only be associated with amount-based contract lines.
-
Define progress payment terms:
-
Assign progress payment and liquidation rates.
-
Assign a distribution code to the progress payment for progress payment liability.
-
Assign defined projects, activities, and amount-based contract lines to the progress payment terms for use during liquidation.
-
Set the progress payment terms to Ready status.
-
-
Define billing and revenue plans for the contract lines.
-
Define the billing amounts for the contract lines.
-
Set the contract processing status to Active.
-
Prepare the progress payment request using the progress payment worksheet.
-
Define an immediate billing plan for the progress payment request.
-
Run the Contracts/Billing Interface process to initiate billing for the progress payment amount.
-
Complete the billing process for the progress payment request.
-
After the contract items are ready for delivery and you are ready to bill, set the billing plans (or events) for amount-based contract lines to Ready status.
-
Run the Contracts/Billing Interface process to generate the regular bill for the items delivered and initiate liquidation of the progress payment amount.
-
Complete the billing process for the items delivered and liquidation of the progress payment.