SFS1500 - Production Variance Report
| Field or Control | Description |
|---|---|
|
Variance Posting Date |
The dates production was closed for accounting. |
|
Prdn Due Date/Shift |
Enter a beginning and end production due date and shift. The Shift field must be between 1 and 3. |
|
Variance Tolerance Amount |
Enter the minimum monetary amount on which you want to display report results. By specifying a minimum monetary amount, you can focus in on those production IDs or production areas with significant variances. Enter 0.00 to report all variances for the production selected. |