Adding Projects to Trees
There are two ways to add a project to a tree:
-
Create the project using the Project General component (PROJECT_GENERAL) and click the Project Tree link in the Project Costing Definition page to insert the project as a node on a tree.
Note:
If you branch a tree, you cannot add a project to the branch from the Project Costing Definition page.
-
In PeopleSoft Tree Manager, select the node to which you want to add an existing project, and click the appropriate icon to insert the project as either a sibling node or a child node.
Use the Tree Manager component (PSTREEMGR) advanced search page to look for trees with a category of PROJECT.
Note:
If there is not a level defined below the parent level, PeopleSoft Tree Manager creates the next level automatically when adding a child project. The newly created level, however, will not have a name or description.
Pages Used to Add Projects to Trees
| Page Name | Definition Name | Usage |
|---|---|---|
|
Assign to Project Tree Page |
PC_PROJ_TREE_SEC |
Assign a project to a specific tree. To access this page, click the Project Tree link in the Project Costing Definition Page. |
|
Tree Manager |
PSTREEMGR |
Insert, delete, or rearrange projects on a project tree. See PeopleTools: PeopleSoft Tree Manager |
Related Topics