Transaction Flow Control

There are two basic ways to control the flow of data coming into PeopleSoft Project Costing:

  1. Set a project or activity to Inactive status.

    In this case, the project and activity do not appear in the prompt lists of the PeopleSoft feeder systems.

  2. Use status control options.

    On the Status Types page, select the analysis types that each feeder system uses; then select a project control action to associate with the analysis type.

    Note:

    No project control action occurs if the Project Control Action box is deselected.

    Values include:

    • Warning: Displays a warning before the system accepts the transaction.

    • Reject: Rejects the transaction.

Instructions on controlling incoming transactions appear in the PeopleSoft Project Costing.