Transaction Flow Control
There are two basic ways to control the flow of data coming into PeopleSoft Project Costing:
-
Set a project or activity to Inactive status.
In this case, the project and activity do not appear in the prompt lists of the PeopleSoft feeder systems.
-
Use status control options.
On the Status Types page, select the analysis types that each feeder system uses; then select a project control action to associate with the analysis type.
Note:
No project control action occurs if the Project Control Action box is deselected.
Values include:
-
Warning: Displays a warning before the system accepts the transaction.
-
Reject: Rejects the transaction.
-
Instructions on controlling incoming transactions appear in the PeopleSoft Project Costing.