Finalizing a Change Package

Once you create the change package and are satisfied with the Change Assistant template, finalize the change package. The finalization process validates the files to confirm that all of the necessary pieces to produce the change package are present and generates a zip file for the entire change package. The zip file enables you to easily migrate your change sets to multiple environments.

To finalize a change project:

  1. Open the change project to finalize.

  2. Select Tools, and then Finalize Change Package from the menu.

  3. Enter the location of the staging directory that you would like zipped up for the change package and click OK.

    Use the browse button to search for the proper directory.

    Change Packager places the zip file in the "<project name>Package" file, using the project name for the file name.