Copying a Project to Multiple Databases
When copying a project to multiple databases, or multiple PeopleSoft systems, use one of the techniques described in this section to ensure that version numbers remain in the correct sequence.
-
Sign off and re-sign onto Application Designer between each project copy to a new environment. This ensures the target environment version is being incremented for each copy. If you do not sign off and re-sign onto the system, the version from the previous target environment will be incremented in the next target environment, which may result in a version discrepancy.
-
Use Change Assistant.
See Change Assistant and Update Manager: Understanding Change Packages.
-
Create a batch file with multiple PSIDE command lines: one for each system.