Copying a Project to Multiple Databases

When copying a project to multiple databases, or multiple PeopleSoft systems, use one of the techniques described in this section to ensure that version numbers remain in the correct sequence.

  • Sign off and re-sign onto Application Designer between each project copy to a new environment. This ensures the target environment version is being incremented for each copy. If you do not sign off and re-sign onto the system, the version from the previous target environment will be incremented in the next target environment, which may result in a version discrepancy.

  • Use Change Assistant.

    See Change Assistant and Update Manager: Understanding Change Packages.

  • Create a batch file with multiple PSIDE command lines: one for each system.

See Copying Definitions Using the Command Line.