Resume a Disaster Recovery Plan Execution

You can resume only the Disaster Recovery (DR) plan executions that are paused. You can not pause or resume prechecks.

  1. Navigate to the Resource page for the standby DR protection group.
  2. Click the Plan Executions link in the Resources panel to navigate to the Plan Executions page for the DR protection group.
    A list of all DR plan executions and prechecks for the protection group is displayed.
  3. The DR plan execution that is currently paused is displayed at the top of the list and has a state of Paused.
  4. Click the DR plan execution that is currently paused to go to the page for the DR plan execution.
  5. Click the Resume button to resume execution of the DR plan execution.
    The DR plan execution moves to an In Progress state and the next queued plan group resumes execution. The DR protection group remains in an Updating state after the DR plan execution has resumed.