View Past and Present Schedule Integration Runs

You can view the status of past and present schedule integration runs.

  1. In the navigation pane, click Design, then Integrations.
  2. Go to the row of the integration on which the scheduled run is defined.
  3. Click Actions Schedule menu icon, then select Schedule.
    The Schedule and future runs page is displayed.
  4. Click Actions Schedule menu icon, then select Track instances.
    The Instances page is displayed. By default, all completed integration runs are displayed.
  5. Click Filter Filter icon to filter the display of integration runs.
  6. Click the file name of the instance.
    A graphical view of the integration flow is displayed.
    For example, if the resubmission resulted in a failure, details are displayed in the activity stream.