| Project Current Forecast Raw Cost - ITD (PLC) |
Shows the Inception to date current Primary Forecast
Project Raw Cost in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Forecast Burdened Cost - ITD
(PLC) |
Shows the Inception to date current Primary Project
Forecast Burdened Cost in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Forecast Revenue - ITD (PLC) |
Shows the Inception to date current Primary Forecast
Project Revenue in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Forecast Margin - ITD (PLC) |
Shows the Inception to date current Primary Forecast
Project Margin in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Forecast Margin Percentage - ITD |
Shows the Inception to date current Primary Forecast
Project Margin Percentage. |
PPM - Project Forecasts |
| Project Current Actual Raw Cost (PLC) |
Shows the Project Actual Raw Cost from current Primary
Forecast Plan version in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Actual Burdened Cost (PLC) |
Shows the Project Actual Burdened Cost from current
Primary Forecast Plan version in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Actual Revenue (PLC) |
Shows the Project Actual Revenue from current Primary
Forecast Plan version in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Actual Margin (PLC) |
Shows the Project Actual Margin from current Primary
Forecast Plan version in Project Ledger currency. |
PPM - Project Forecasts |
| Project Current Actual Margin Percentage |
Shows the Project Actual Margin Percentage from current
Primary Forecast Plan version. |
PPM - Project Forecasts |
| Project Current ETC Raw Cost (PLC) |
Shows the Project Estimate to Complete Raw Cost from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current ETC Burdened Cost (PLC) |
Shows the Project Estimate to Complete Burdened Cost from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current ETC Revenue (PLC) |
Shows the Project Estimate to Complete Revenue from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current ETC Margin (PLC) |
Shows the Project Estimate to Complete Margin from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current ETC Margin Percentage |
Shows the Project Estimate to Complete Margin Percentage
from current Primary Forecast Plan version. |
PPM - Project Forecasts |
| Project Current EAC Raw Cost (PLC) |
Shows the Project Estimate at Completion Raw Cost from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current EAC Burdened Cost (PLC) |
Shows the Project Estimate at Completion Burdened Cost
from current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current EAC Revenue (PLC) |
Shows the Project Estimate at Completion Revenue from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current EAC Margin (PLC) |
Shows the Project Estimate at Completion Margin from
current Primary Forecast Plan version in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current EAC Margin Percentage |
Shows the Project Estimate at Completion Margin
Percentage from current Primary Forecast Plan version. |
PPM - Project Forecasts |
| Project Current Budget Raw Cost - ITD (PLC) |
Shows the Inception to date current Approved Budget
Project Raw Cost in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Burdened Cost - ITD (PLC) |
Shows the Inception to date current Primary Project
Forecast Burdened Cost in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Revenue - ITD (PLC) |
Shows the Inception to date current Approved Budget
Project Revenue in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Margin - ITD (PLC) |
Shows the Inception to date current Approved Budget
Project Margin in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Margin Percentage - ITD |
Shows the Inception to date current Approved Budget
Project Margin Percentage. |
PPM - Project Budgets |
| Project Current Budget Raw Cost (PLC) |
Shows the Project Raw Cost from current Approved Budget
Plan version in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Burdened Cost (PLC) |
Shows the Project Burdened Cost from current Approved
Budget Plan version in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Revenue (PLC) |
Shows the Project Revenue from current Approved Budget
Plan version in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Margin (PLC) |
Shows the Project Margin from current Approved Budget
Plan version in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Budget Margin Percentage |
Shows the Project Margin Percentage from current Approved
Budget Plan version. |
PPM - Project Budgets |
| Project Current BAC Raw Cost (PLC) |
Shows the Project Budget at Completion Raw Cost from
current Approved Budget Plan version in Project Ledger currency. |
PPM - Project Budgets |
| Project Current BAC Burdened Cost (PLC) |
Shows the Project Budget at Completion Burdened Cost from
current Approved Budget Plan version in Project Budget at Completion
Ledger currency. |
PPM - Project Budgets |
| Project Current BAC Revenue (PLC) |
Shows the Project Budget at Completion Revenue from
current Approved Budget Plan version in Project Budget at Completion
Ledger currency. |
PPM - Project Budgets |
| Project Current BAC Margin (PLC) |
Shows the Project Budget at Completion Margin from
current Approved Budget Plan version in Project Budget at Completion
Ledger currency. |
PPM - Project Budgets |
| Project Current BAC Margin Percentage |
Shows the Project Budget at Completion Margin Percentage
from current Approved Budget Plan version. |
PPM - Project Budgets |
| Project Current Versus Original BAC Raw Cost Variance
(PLC) |
Shows the Variance between current and/original Approved
Budget at Completion Raw Cost in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Versus Original BAC Burdened Cost
Variance (PLC) |
Shows the Variance between current and/original Approved
Budget at Completion Burdened Cost in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Versus Original BAC Revenue Variance
(PLC) |
Shows the Variance between current and/original Approved
Budget at Completion Revenue in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Versus Original BAC Margin Variance
(PLC) |
Shows the Variance between current and/original Approved
Budget at Completion Margin in Project Ledger currency. |
PPM - Project Budgets |
| Project Current Versus Original BAC Margin Percentage
Variance |
Shows the Variance between current and/original Approved
Budget at Completion Margin Percentage. |
PPM - Project Budgets |
| Project Current Versus Original EAC Raw Cost Variance
(PLC) |
Shows the Variance between current and/original Estimate
at Completion Primary Forecast Raw Cost in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current Versus Original EAC Burdened Cost
Variance (PLC) |
Shows the Variance between current and/original Estimate
at Completion Primary Forecast Burdened Cost in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current Versus Original EAC Revenue Variance
(PLC) |
Shows the Variance between current and/original Estimate
at Completion Primary Forecast Revenue in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current Versus Original EAC Margin Variance
(PLC) |
Shows the Variance between current and/original Estimate
at Completion Primary Forecast Margin in Project Ledger
currency. |
PPM - Project Forecasts |
| Project Current Versus Original EAC Margin Percentage
Variance |
Shows the Variance between current and/original Estimate
at Completion Primary Forecast Margin Percentage. |
PPM - Project Forecasts |
| Project Current EAC Forecast Versus Current BAC Raw Cost
Variance (PLC) |
Shows the Variance between current EAC Primary Forecast
and current Approved BAC Raw Cost in Project Ledger currency. |
PPM - Project Forecasts, PPM - Project Budgets |
| Project Current EAC Forecast Versus Current BAC Burdened
Cost Variance (PLC) |
Shows the Variance between current EAC Primary Forecast
and current Approved BAC Burdened Cost in Project Ledger
currency. |
PPM - Project Forecasts, PPM - Project Budgets |
| Project Current EAC Forecast Versus Current BAC Revenue
Variance (PLC) |
Shows the Variance between current EAC Primary Forecast
and current Approved BAC Revenue in Project Ledger currency. |
PPM - Project Forecasts, PPM - Project Budgets |
| Project Current EAC Forecast Versus Current BAC Margin
Variance (PLC) |
Shows the Variance between current EAC Primary Forecast
and current Approved BAC Margin in Project Ledger currency. |
PPM - Project Forecasts, PPM - Project Budgets |
| Project Current EAC Forecast Versus Current BAC Margin
Percentage Variance |
Shows the Variance between current EAC Primary Forecast
and current Approved BAC Margin Percentage. |
PPM - Project Forecasts, PPM - Project Budgets |
| Project Remaining Current Budget Raw Cost (PLC) |
Shows the remaining current Approved Budget Raw Cost
amount calculated as Budget at Completion current Raw Cost - total
Actual Raw Cost in Project Ledger currency. |
PPM - Project Budgets, PPM - Project Costs |
| Project Remaining Current Budget Burdened Cost
(PLC) |
Shows the remaining current Approved Budget Burdened Cost
amount calculated as Budget at Completion current Burdened Cost - total
Actual Burdened Cost in Project Ledger currency. |
PPM - Project Budgets, PPM - Project Costs |
| Project Remaining Current Budget Cost with Commitments
(PLC) |
Shows the remaining current Approved Budget Burdened Cost
amount calculated as Budget at Completion current Burdened Cost - total
Actual Burdened Cost - total Committed Cost in Project Ledger
currency. |
PPM - Project Budgets, PPM - Project Costs, PPM - Project
Commitments |
| Project Remaining Current Budget Revenue (PLC) |
Shows the remaining current Approved Budget Revenue
amount calculated as Budget at Completion current Revenue - total Actual
Revenue amount in Project Ledger currency. |
PPM - Project Budgets, PPM - Project Revenue |