Reset Environment

The Reset Environment script enables you to clear all Data Management setup and data resetting the entire business process environment. You can then reconfigure the integration process as needed. This process accepts a Yes or No confirmation parameter and allows you to specify a reason for the reset.

Note:

When the Reset Environment process is executed, data cannot be recovered.

To run the Reset Environment script:

  1. Complete the steps for scheduling a maintenance script.

    For more information, see Scheduling Maintenance Scripts in the Job Scheduler.

  2. From the Schedule Job page, select Reset Environment.

  3. From the Reset Environment page, and then from Confirm Delete, select Y (yes) to confirm the reset of the environment.

    Otherwise, enter N (No).

  4. In Reason for Delete, specify the reason for resetting the environmen.

  5. Click OK.